Soil Stabilisation & Bulk Earthworks | St Asaph Wales
Soil Stabilisation in Wales
The contract, which we undertook for Adonis Construction, was for an AD Plant in Waen which was being developed by Biogen Ltd for the North Wales Consortium of Councils.
The AD Plant, once completed, will process on average 22,500 tonnes per year and will provide sufficient power for 1,500 homes continuously.
The works carried out by ourselves involved a Bulk Earthworks operation across the site prior to Lime Modification and Soil Stabilisation taking place.
Once the Earthworks Operation had been carried out all of the Bulk Fill material was Lime Modified to achieve a CBR of not less than 5% with the surface material being Lime + Cement Stabilised to provide a Capping Replacement with a CBR of not less than 15% and a Sub-Base Replacement with a CBR of not less than 30%.
The treated material was then compacted, trimmed to tolerance and bitumen emulsion curing agent applied to the surface.
Compliance testing was carried out throughout the entire operation to confirm that the required specifications had been met.
Soil Stabilisation Projects
Cement Stabilisation Contractor |...
Cement Stabilisation at Chesterfield When Moorhead Excavations, who were carrying out the Civ...
[Read more]Cement Stabilisation Contractor...
Cement Stabilisation at Tutbury In early January 2013 we were approached by O'Brien Contr...
[Read more]Lime Modification | Speke
Lime Modification at Speke After successfully carrying out Soil Stabilisation on many pr...
[Read more]Lime Stabilisation | Daresbury...
Lime Stabilisation at Daresbury Park, Runcorn The area to be stabilised was part of a Marshal...
[Read more]Lime Stabilisation | Gateshead
Lime Stabilisation at Gateshead The site was a former Staithes Gas Works in Dunston, Gateshea...
[Read more]Lime Stabilisation | Normanton
Lime Stabilisation at Normanton Several contracts have established a strong working relations...
[Read more]Lime Stabilisation Contractor |...
Lime Stabilisation at Altham Having already carried out Soil Stabilisation works on Phase 1 o...
[Read more]Soil Stabilisation & Bulk...
Soil Stabilisation in Wales The contract, which we undertook for Adonis Construction, was for...
[Read more]Soil Stabilisation | Birchwood...
Soil Stabilisation at Birchwood Park, Warrington A new 3 storey building and car park was bei...
[Read more]Soil Stabilisation | Butlins,...
Soil Stabilisation at Butlins, Minehead We were approached by McGoff & Byrne t...
[Read more]Soil Stabilisation | Droitwich
Soil Stabilisation at Droitwich This new development at Stonebridge Business Park...
[Read more]Soil Stabilisation | Market Drayton
Soil Stabilisation at Market Drayton We were contacted by McPhillips (Wellington)...
[Read more]Soil Stabilisation | Monks Cross...
Lime Stabilisation at Monks Cross, York T R Stabilisation have worked with Moorhead Excavatio...
[Read more]Soil Stabilisation | Riverside...
Soil Stabilisation at Riverside House, Warrington The area to be stabilised was part of...
[Read more]Soil Stabilisation | Whatmore UK...
Soil Stabilisation at Altham The site was being developed by Whatmore UK to add to a large In...
[Read more]Soil Stabilisation | Windfarm
Soil Stabilisation at Coal Clough Windfarm Due to the close proximity of this site to our Hea...
[Read more]Soil Stabilisation at Knutsford
Soil Stabilisation at Knutsford The project, where we carried out Civil Engineerin...
[Read more]Soil Stabilisation Contractor |...
Soil Stabilisation at Ferrybridge Power Station Having previously carried out Soil Stabilisat...
[Read more]Soil Stabilisation Contractor...
Soil Stabilisation at Telford An expansion was taking place at Ercall Wood College in Telford...
[Read more]