Soil Stabilisation on Site This Week!

This week will be one of the busiest weeks we have had since the company formed, with 5 contracts running simultaneously.  Updates and details from all of the contracts are listed below:

Birmingham Airport

We are still assisting Volker Fitzpatrick Colas JV on this contract and are due to remain on site for the next few months.

Droitwich

We have now been on site for John Sisk for 3 weeks and despite the almost constant rain throughout the UK , have managed to progress the works well and stay on target.

Bolton

Works are now coming to a close on the school development we have been working on in Burnley and a case study will be uploaded to our web-site in due course.

Burnley

The Bulk Earthworks started on this contract last week and the Soil Stabilisation works are due to commence later this week.  We will keep you posted as and when the works develop.

York

We are back on site for Moorhead Excavations carrying out some further works on the Monks Cross development this week.  Again, photos and videos will be uploaded as the works progress.

Tags: , , , , , , , , , , , , , ,

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>